Home Additions in Los Angeles
A home addition is often the best way to get more space without leaving a neighborhood you love. A single-room addition usually takes 4 to 7 months to build once permits are in hand. SAS Builds plans, permits, and builds additions that look like they were always part of the house.

- Seamless tie-insRooflines, floors, and finishes matched so the new space looks original.
- Permits handledWe check zoning first and take the plans through plan check and inspections.
- Price before workA written scope, schedule, and price before construction starts.
Types of additions we build
Most additions fall into one of three shapes. The right one depends on your lot, your zoning, and how you want the house to live.
- Ground-floor room additions: a new bedroom suite, family room, or a larger kitchen built out into the yard
- Second-story additions: new space built on top of the existing house, which keeps your yard intact
- Bump-outs: smaller extensions that add a few feet where it matters most, like a kitchen or primary bath

Making new space look original
A good addition reads as part of the house, inside and out. That comes from matching what is already there: the roof pitch and eave lines, the window style, the exterior finish, and the ceiling heights.
Inside, the floor is usually the hardest match. Sometimes the best answer is to run new flooring through the old rooms too, so there is no seam where the addition begins. We talk through those choices before design is final, because they change the scope.

Second-story additions need an engineer first
Before anyone designs a second story, a structural engineer has to confirm the existing foundation and framing can carry it. Many older Los Angeles houses need foundation work, new shear walls, or new posts and beams to take the extra load.
A second story also changes how you live during the work. The roof comes off, so most families move out for at least part of construction. We plan that with you up front so there are no surprises.

What shapes the budget
An addition is often more expensive per foot than people expect, and the reasons are specific. You pay to connect old to new: matching rooflines, tying into the existing foundation, and blending finishes. And each trade costs nearly as much to mobilize for one room as for a whole house.
The existing house matters too. New space can trigger upgrades to what is already there, like a larger electrical panel, a bigger HVAC system, or a new sewer connection. Older houses also hide surprises behind the walls, and an addition opens those walls, so a contingency belongs in every addition budget.
We price an addition after walking the house and the lot. You get a written scope, a schedule, and a clear price before work starts.
Plan your addition with us
Start the short project questionnaire and we will book a call, then walk the house and lot with you to see what fits.
Living at home during an addition
Many families stay home during a ground-floor addition. Most of the work happens outside the existing walls, and the opening into the house is cut near the end, once the new rooms are closed in.
We seal off the work area, protect floors along the path the crew uses, and agree on working hours and where the crew parks. If the kitchen or a bathroom will be out of service for a stretch, we tell you when, and for how long, before it happens.
How long an addition takes
A single-room addition usually takes 4 to 7 months of construction. Design and permitting come first and often take as long again.
Plan check in Los Angeles typically takes 3 to 9 months, and longer on hillside or coastal lots. Each round of corrections usually adds four to eight weeks, so a complete first submittal is the best way to save time.
Permits and zoning
Every addition needs a building permit. Zoning sets the limits: how close you can build to the property lines, how tall you can go, and how much floor area the lot allows.
Inside the City of Los Angeles, hillside lots may fall under the Baseline Hillside Ordinance, which generally limits floor area and grading more tightly than flat lots. Fire hazard zones and the Coastal Zone add their own requirements. We check these at the start so the design fits what the city will approve.
Frequently asked questions
What affects the cost of a room addition?
Mostly the size and the connection to the existing house: matching the roof and foundation, upgrades the existing systems need, the site, and your finishes. Hillside lots and structural work add the most. We give you a written price after walking the property, before any work starts.
Should I add a second story or build out?
Building out on the ground floor is usually simpler, because a second story often needs foundation and framing upgrades and requires removing the roof. A second story makes sense when the lot has no room to expand or when keeping the yard matters most.
How long does a home addition take?
A single-room addition typically takes 4 to 7 months of construction. Add design and permitting beforehand, which in Los Angeles commonly takes 3 to 9 months for plan check alone.
Can I live in my house during an addition?
Often yes for a ground-floor addition, since most of the work happens outside the existing walls until the final tie-in. A second-story addition usually requires moving out for part of the job, because the roof is removed.
Do I need an architect for an addition?
You need permit-ready drawings and structural engineering. You can hire an architect directly and have us build from their plans, or work with us design-build, where we coordinate design and construction as one team.
Planning guides
- Planning ToolHow Much Space Will You Really Need?Right-size your program before you commit to square footage.
- GuideHow Long Does It Take to Build a Custom Home?Realistic timelines for custom homes, remodels, and additions.
- GuideWhat to Expect During ConstructionA month-by-month picture of life while your project is underway.